No Maryland lien exists until a court orders one
Reminder material only: in Maryland there is no lien document recorded in the land records. A claimant establishes a mechanic's lien only by circuit-court proceedings; no lien exists until a court orders one.
Reminder material only. This page does not work out your deadline. Your own records and your attorney set that.
Contractor vs. subcontractor is defined by who you signed with
Reminder material only: for Maryland lien purposes, a contractor has a contract with the owner. Anyone whose contract is with anyone else, including a supplier selling to a subcontractor, is a subcontractor.
Reminder material only. This page does not work out your deadline. Your own records and your attorney set that.
Subcontractor Notice of Intent to Claim a Lien within 120 days
Reminder material only: subcontractors must give the owner written Notice of Intent to Claim a Lien within 120 days after doing the work or furnishing the materials, using the statutory form, by certified mail or personal delivery. Direct contractors skip this step.
Reminder material only. This page does not work out your deadline. Your own records and your attorney set that.
Single-family owner-occupied limit on a subcontractor's lien
Reminder material only: on a home being built on the owner's own land for the owner's own residence, a subcontractor's lien cannot exceed what the owner still owes the contractor when the notice arrives, and an owner who already paid the contractor in full before receiving notice is protected.
Reminder material only. This page does not work out your deadline. Your own records and your attorney set that.
Petition to Establish a Mechanic's Lien within 180 days
Reminder material only: every claimant must file the Petition to Establish a Mechanic's Lien within 180 days after work was finished or materials were last furnished.
Reminder material only. This page does not work out your deadline. Your own records and your attorney set that.
Lien enforcement expires 1 year from the day the petition was filed
Reminder material only: enforcement of a Maryland mechanic's lien expires 1 year from the day the petition was filed.
Reminder material only. This page does not work out your deadline. Your own records and your attorney set that.
15 percent improvement threshold, no minimum dollar amount
Reminder material only: every building erected, and every building repaired, rebuilt, or improved to the extent of 15 percent of its value, is subject to lien, with no minimum dollar amount in the statute. Sodding, seeding, grading, landscaping, and paving are expressly covered work.
Reminder material only. This page does not work out your deadline. Your own records and your attorney set that.
Prompt-payment clocks: 7 days / 30 days, with a home improvement carve-out
Reminder material only: on private construction contracts, undisputed amounts are due 7 days after the contract's stated payment date (or within 30 days of occupancy permit or possession if no date is stated), and contractors must pay subcontractors within 7 days of receiving payment. Section 9-302 does not apply to home improvement contracts by MHIC-licensed contractors.